Touch Hill Place : Project Progress as of July 31, 2009
July 31, 2009
*Building 1 Construction Work Progress as of July 31, 2009
- Sub-Roof Aluminium is 100% completed.
- Roof Tiling is 70% of work completed.
- Roof Water Tank is 30% of work completed.
*Swimming Pool Progress
- Foundation is100% completed
- Pool & Club House Slab is 50% of work completed