Touch Hill Place : Project Progress as of September 15, 2009

September 15, 2009

*Progress on Structural Work

  • Roof Tile is now 80% Completed.
  • Water Tank on Roof is 100% Completed.
  • Internal Block Wall & Plastering Work are now 80% Completed.
  • External Block Wall & Plastering Work are now 50% Completed.
  • Aluminium Glass Wall & Door are now 30% Completed.
  • Waste Water Treatment Tank is 70% Completed.