Touch Hill Place : Project Progress as of October 16, 2009

October 16, 2009
  • "Tower Dome" Tiling Work is now 90% completed.
  • Internal Block Wall & Plastering Works are Now 90% completed.
  • External Block Wall & Plastering Works are Now 80% completed.
  • Aluminium Glass Wall & Door Works are Now 65% completed.
  • Aluminium Glass Wall & Door are now 30% Completed.
  • Swimming Pool - Reinforced Wall Casting and Plastering Works are now 100% completed