Touch Hill Place : Project Progress as of November 30, 2009

  • Tower Dome Roof & Water Tank Works are now 100% Completed.
  • Internal & External Block Wall With Plastering Works are now 99% Completed.
  • Aluminium Glass Wall & Door Works are now 80% Completed.
  • Internal Painting Work is now 90% Completed.
  • External Painting Work is now 70% Completed.
  • External Drainage & Fence Works are now starting from Back of Project Site.
  • Swimming Pool Deck - Ground Beam Work is now 100% Completed.
  • Scrap House & Waste Water Tank Works are now 100% Completed.