Touch Hill Place : Project Progress as of December 30, 2009

  • Aluminium Glass Wall & Doors are 99% completed.
  • External & Internal Paint is now 90% completed.
  • External Stainless Handrail at Terrace is now 85% completed.
  • Entrance Canopy is now 85% completed.
  • Swimming Pool & Club House Structural Works are 90% completed.
  • Swimming Pool & Club House Architectural Works are 30% completed.
  • External Block Fence is now 80% completed.
  • External Drainage Piping Work - Just Started
  • Electric Power Plant is now100% completed.