Touch Hill Place : Project Progress as of February 28, 2010

  • Aluminium Glass Wall & Doors are 100% completed.
  • External & Internal Paint is now 100% completed.
  • External Stainless Handrail at Terrace is now 100% completed.
  • Entrance Canopy is now 100% completed.
  • Roof Garden on 3rd Floor is now is now 100% completed.
  • Swimming Pool & Club House Structural Works are 100% completed.
  • Swimming Pool & Club House Architectural Works are 90% completed.
  • External Block Fence is now 100% completed.
  • External Drainage Piping Work - is now 100% completed.
  • Electric Power Plant is now100% completed.