Touch Hill Place : Project Progress as of May 31, 2009

June 9, 2009

*Structural Work Progress

  • 9th Floor Concrete Slab Casting is now 100% completed
  • Project Schedule for Roof Beam & Roof Fin & Roof Deck will be completed by June30, 2009

*Finishing Work Progress

  • Wall & Plastering Work has been comepleted 60% (1st - 5th Floor)

*Swimming Pool Construction Work Schedule

  • 8 x 20 m. Swimiming Pool Construction will be started by June, 2009