Touch Hill Place : Project Progress as of June 30, 2009

June 30, 2009

*Progress on Structural Work

  • Roof Beam & Fin is now 90% completed.
  • Steel Roof Frame & Support has been 50% completed.
  • Swimming Pool Foundation Work has been 20% completed.

*Progress on Masonly Work

  • 1st-6th floor - Block Wall is now 90% completed, and 80% completed for 7th floor.
  • 1st-5th floor - Wall Plastering is 75% completed.